Home / Guides / Site safety kit guide
Guides · PPE & Fire Protection

The safety kit a construction site holds.

The short version: the OSH law (RA 11058, its rules in D.O. 198-18, and D.O. 13-98 for construction) makes the contractor provide the protective equipment, the gas testing, the lockout and the first aid the work calls for, at no cost to the worker. The Fire Code (RA 9514 and its IRR) sets the extinguisher, exit, hose and pump side. This page lists the items sites and safety officers actually order, what each covers, how many, and what to send for a quote. Where a safety officer's plan or a BFP requirement exists, it governs. The per-worker PPE list is on the PPE checklist.

PPE & safety supply →Fire protection supply →

Who requires what

Plain summary · the law and the safety plan set the exact list for each site

RuleWhat it asks of the siteItems that follow
RA 11058 and D.O. 198-18 (the OSH law and its rules)The employer provides PPE free of charge, fit for the hazard and replaced when worn; a safety officer and a first-aider on site; hazard and exit signage; safe use of equipment; treatment facilities scaled by headcountRespirators and filters, insulating gloves, lockout, gas detectors, first-aid kit, eyewash, signage
D.O. 13-98 (construction safety and health)A construction safety and health program approved by DOLE, with an emergency and fire plan, PPE by trade, safe access and egress, and temporary facilitiesEscape routes and ladders, an extinguisher on every floor, an alarm everyone can hear, a first-aid station
OSHS Rules 1070, 1080, 1210 and 1940Exposure limits and atmosphere testing; PPE; electrical work made safe before it starts; fire protection and control in the workplaceGas detectors and calibration, respirator change schedules, locks and tags, extinguishers and hose
RA 9514 and its IRR (the Fire Code)Portable extinguishers by hazard and travel distance; marked, lit exits; standpipe and hose; a fire department (siamese) connection and a fire pump where the plan calls for a standpipe or sprinklers; fire safety during construction and demolition; a Fire Safety Inspection Certificate before occupancyExtinguishers, fire blankets, exit signs and emergency lights, hose and nozzles, siamese connections, fire pumps

The two sides overlap on purpose: DOLE inspects the safety program and the BFP inspects the fire side, and both expect the equipment to be on site, marked and in date, not on order.

The checklist

By hazard · what each item covers · what to hold on site

Respiratory protection

ItemWhat it is forWhat to holdRating
Half-face reusable respirator (3M 6200, 3M 7502, Shigematsu double-valve half mask)Concrete cutting and grinding, welding fume, paint and solvent with the right filterOne per exposed worker, fit-checked; sizes small, medium and largeNIOSH 42 CFR 84 / EN 140
Full-face respirator (Shigematsu TW088)Same duty with eye protection: spray painting, chemical handling, confined space with fumesOne per painter or chemical handlerNIOSH 42 CFR 84 / EN 136
P100 particulate filters (3M 2091, 3M 7093)Silica dust from cutting or grinding concrete, welding fume, lead paint, oil mistA pair fitted plus a spare pair per respirator; replace when breathing gets hard, or when damaged or wetNIOSH P100: 99.97 percent, oil-proof
Organic vapour and acid gas cartridges (3M 6001)Solvents, paints, adhesives, sealantsChange on a schedule set by the exposure, not by smell alone; pair with a P100 pre-filter for spray workNIOSH OV / OV-AG
Disposable N95 or FFP2Nuisance dust and short jobsNot for a day of silica cutting; use a P100 respirator for thatNIOSH N95 / EN 149 FFP2

Electrical work

ItemWhat it is forWhat to holdRating
Insulating rubber gloves (Regeltex Electrovolt, Class 00 to 4, Showa, UT)Work on or near live panels, feeders and switchgearOne pair per electrician in the class for the voltage; air-test before each use, electrical retest every 6 months in serviceASTM D120 / IEC 60903 — Class 00: 500 V · Class 0: 1,000 V · Class 1: 7,500 V · Class 2: 17,000 V · Class 3: 26,500 V · Class 4: 36,000 V (maximum use voltage, AC)
Leather protector glovesWorn over the rubber gloves against cuts and abrasionOne pair per pair of rubber gloves; never worn alone for electrical workASTM F696
Lockout station (compact 4-hanger, 16-hanger electrical and valve)A fixed board at the panel room or workshop with padlocks, hasps, tags, breaker and valve lockoutsOne padlock per worker who works on the feed, one key each; a hasp when more than one crew is on the same isolation; tags dated and signedOSHS Rule 1210 and the site safety program; NFPA 70E as reference
Portable lockout kit (electrical lockout kit)A crew kit for isolations away from the board: MCB and MCCB lockouts, plug lockouts, hasps, tags, padlocksOne kit per electrical crew; restock tags and padlocks as they are usedAs above
Voltage testerProve dead before the lock goes on and before work startsOne per electrician, rated for the panel voltageIEC 61243-3

Confined space

ItemWhat it is forWhat to holdAlarm points
Single-gas detector, oxygen (Honeywell BW Clip O2)Tanks, manholes, pits, lift shafts and any space where air can be displacedOne per entrant and one for the attendant; bump test each day of useLow 19.5 percent · high 23.5 percent
Single-gas detector, H2S (BW Clip H2S, 2-year)Septic tanks, sewer manholes, sumps, sewage treatment plantsOne per entrant where sewage or organic decay is present; maintenance-free 2-year unit, bump test before useLow 10 ppm · high 15 ppm
Single-gas detector, COGenerators and engines run in enclosed or below-grade areasOne per crew working near engines indoorsLow 35 ppm · high 200 ppm
Multi-gas detector (BW GasAlertMicroClip XL: O2, LEL, H2S, CO)The entry-permit standard: pre-entry test and continuous monitoring inside the spaceOne per entry team; bump test each day of use, calibrate on the maker's schedule; keep the log with the permitLEL low 10 percent, plus the O2, H2S and CO points above
Retrieval tripod, winch and full-body harnessGetting an entrant out without sending a second person inOne set per vertical entry; harness with a dorsal D-ring per entrantANSI Z359 / EN 361 harness
Forced-air ventilation blowerClearing and keeping the space ventilated before and during entryOne per entry, with ducting to reach the workSized to the space; the safety plan sets the air changes

Single-gas clips are for a known hazard or an attendant at the opening. A permit entry needs the four-gas reading before anyone goes in, an attendant who stays outside, a way to pull the entrant out, and a permit that records the readings.

Fire and exit

ItemWhat it is forWhat to holdStandard
Portable extinguishers, ABC dry chemical (Spiderking, Drychem)Wood, paper, fuel and electrical fires on a working floorAt least one per floor and one at every hot-work station, fuel store, generator and site office; a Class A unit within 23 m of any point, a Class B unit within 9 to 15 m of fuel areasFire Code IRR / NFPA 10; monthly visual check, annual service, hydrostatic test every 12 years
CO2 or clean-agent extinguisher (Spiderking HCFC)Panel rooms, generators, server and control rooms — no powder residueOne at each electrical room and generatorFire Code IRR / NFPA 10; CO2 hydrostatic test every 5 years
Fire blanket (1.8 × 1.8 m quick release, Spiderking)Smothering a small fire or a burning worker at hot-work stations, canteens and the welding bayOne per hot-work station and one per canteenEN 1869 / BS EN 1869
Fire hose, hose reel and nozzlesHose lines from the standpipe as the building rises; hose cabinets on each floor once the riser is inPer the fire-protection plan; the standpipe follows the floors so a hose reaches the working levelFire Code IRR / NFPA 14
Siamese connection and wye (siamese twin)The two-inlet connection at street level where the BFP pumper feeds the standpipe or sprinkler riser; a wye splits one supply line into two hose linesOne siamese per riser, thread and cap to the BFP's pattern; wyes and adapters with the hose stockFire Code IRR / NFPA 14 and 13
Fire pumps (NM Fire UL/FM sets: end-suction, split-case, vertical in-line)Feeding the standpipe or sprinkler system where the approved plan calls for one, with jockey pump and controllerSized to the plan's flow and pressure; portable engine pumps for site water and early-stage coverNFPA 20 as adopted by the Fire Code IRR
Foldable escape ladder (Miller ARL-300)A second way down from upper-floor site offices, bunkhouses and mezzanines where the second stair is not yet builtOne per occupied upper-floor room without a second exit; length to reach the ground; hooks checked monthlyFire Code IRR means-of-egress rules; D.O. 13-98 safe access and egress
Exit signs and emergency lightsMarking and lighting every exit route in occupied site buildings when the power dropsBattery-backed units at every exit and change of direction on the routeFire Code IRR / NFPA 101; D.O. 198-18 signage
Alarm and muster pointA bell, siren or air horn everyone on site can hear, and a marked assembly pointOne alarm point per floor or zone; the assembly point on the site plan and the signboardD.O. 13-98 emergency plan
Hot-work permit kitFire watch with an extinguisher in reach, welding screens, spark blanketsOne set per welding or cutting station; fire watch stays 30 minutes after the work stopsNFPA 51B as reference; OSHS Rule 1940

First aid and emergency

ItemWhat it is forWhat to holdStandard
First-aid kit (25-person, 50-person ANSI kits, Spiderking)Cuts, burns, eye injuries and sprains before the worker reaches a clinicOne kit sized to the headcount at the site office and one per remote work area; restocked monthly and checked for expiry; a trained first-aider on every shiftD.O. 198-18 first-aider and facilities by headcount; ANSI Z308.1 kits
Eyewash station (Fendall portable 16-gallon, Speakman wall-mounted)Chemical, cement, battery acid and grinding-dust eye injuriesWithin 10 seconds of the hazard, a 15-minute flush; solution changed by the maker's dateANSI Z358.1
Stretcher or spine boardMoving an injured worker off a floor or out of a trenchOne per site, at the first-aid stationD.O. 13-98 emergency plan
Emergency boardClinic, hospital, BFP and DOLE numbers, the first-aider's name, the assembly pointAt the gate and the site officeD.O. 198-18 OSH information

How many, and how often to check

Working figures for planning the order · the safety plan sets the final count

ItemHow manyCheck
Respirators and P100 filtersOne respirator per exposed worker; a fitted pair of filters plus a spare pair eachSeal check at each wearing; replace filters when breathing resistance rises, or when damaged or wet; cartridges on the change schedule
Insulating glovesOne pair of rubber gloves and one pair of protectors per electricianVisual and air test before each use; electrical retest every 6 months in service; store flat, away from sun and oil
LockoutOne padlock and one key per worker on the isolation; hasps and tags in stockTags filled in and signed; the board restocked as padlocks go out
Gas detectorsOne per entrant and attendant; a four-gas unit per entry teamBump test each day of use; calibrate on the maker's schedule; 2-year clips are replaced, not calibrated
ExtinguishersAt least one per floor, per hot-work station, fuel store, generator and office; within 23 m travel for Class AMonthly visual (gauge, seal, tag); annual service; hydrostatic test every 12 years for dry chemical, every 5 for CO2
Escape laddersOne per occupied upper-floor room without a second stairHooks, rungs and straps checked monthly; kept at the window, not in a store room
First aid and eyewashOne kit per site office and remote area; eyewash at each chemical or grinding stationRestock monthly and check expiry dates; eyewash solution changed by the maker's date

Keep the dates on a single register: filter change, glove test, detector bump and calibration, extinguisher service, first-aid restock. It is what the DOLE and BFP inspectors ask to see, and it tells you when to reorder.

What to send for a quote

Everything on this page is stocked or sourced from Dasmariñas, Cavite — 3M and Shigematsu respirators and filters, Regeltex and Showa insulating gloves, lockout stations and kits, Honeywell BW gas detectors, Spiderking and Drychem extinguishers, fire blankets, hose and siamese connections, NM Fire pumps, first-aid kits and eyewash — and delivered nationwide. Send the headcount and the list and we quote it back the same day.

Common questions

What PPE must a construction site provide under the OSH law?

RA 11058 and its rules (D.O. 198-18) make the employer provide PPE free of charge, matched to the hazard and replaced when worn — head, eye, hearing, hand, foot, fall and respiratory protection as the task calls for. D.O. 13-98 adds the construction safety and health program that lists the PPE per trade. The per-task list is on the PPE checklist page.

Is a P100 filter the same as an N95?

No. An N95 stops 95 percent of test particles and is not oil-resistant; a P100 stops 99.97 percent and is oil-proof. For silica dust from cutting or grinding concrete, welding fume and lead paint, use a half-face respirator with P100 filters; keep N95 for short, light dust jobs.

Which class of insulating gloves for 220 V and 440 V site work?

Class 00 is rated to 500 V AC and Class 0 to 1,000 V AC; either covers 220 V and 440 V panels and feeders, and Class 0 is the usual site choice. Class 1 to 4 (7,500 to 36,000 V) are for utility and high-voltage work. Always wear leather protectors over the rubber and air-test the gloves before each use.

Do I need a single-gas or a multi-gas detector for confined space?

For a permit entry the standard is a four-gas unit — oxygen, combustible (LEL), H2S and CO — for the pre-entry test and continuous monitoring. Single-gas clips (O2, H2S or CO) suit an attendant, a known single hazard, or a worker near generators or sewage lines. Bump test before each use.

How many fire extinguishers does a site need?

The Fire Code IRR follows NFPA 10: a Class A extinguisher within 23 m of any point, and a Class B unit within 9 to 15 m of fuel, generator and hot-work areas — so at least one per floor and one at every hot-work station, fuel store and site office. ABC dry chemical covers most of the site; CO2 or clean-agent for panels and electrical rooms. The BFP inspector confirms the count for the building.

When does a building under construction need a fire pump and siamese connection?

When the approved fire-protection plan calls for a standpipe or sprinkler system — usually mid-rise and larger buildings — the riser is fed by a fire pump sized to NFPA 20 and has a siamese (fire department) connection outside for the BFP pumper. As the structure goes up, the standpipe should follow the floors so a hose line reaches the working level. Send the plan and we quote the pump set, hose and connections against it.

What does Southend supply from this list?

Respirators, P100 filters and cartridges, insulating gloves, lockout stations and kits, single- and multi-gas detectors, escape ladders, extinguishers, fire blankets, hose and siamese connections, fire pumps, first-aid kits and eyewash — stocked or sourced from Dasmariñas, Cavite and delivered nationwide. Send the headcount and the list for a Same-Day Quote.

Related

PPE & safety supply →Fire protection supply →Guide: construction site PPE checklist →Electrical supply →Pumps & motors →All guides →

Standards referenced. RA 11058 and DOLE D.O. 198-18 · D.O. 13-98 · OSHS Rules 1070, 1080, 1210 and 1940 · RA 9514 (Fire Code) and its IRR · NFPA 10, 13, 14, 20, 51B, 70E, 101 and 241 as referenced · ASTM D120 and F696, IEC 60903 · NIOSH 42 CFR 84, EN 140, 136 and 149 · ANSI Z358.1, Z308.1 and Z359. This page is for planning and ordering only, not a safety program — the site's DOLE-approved construction safety and health program, the safety officer's plan and the BFP's requirements govern.